The Railway Chronicle

The Railway Chronicle is brought to you by www.steamtu.be "Steam Tube" is not responsible for external /third party news items.

Their presence on here does not mean we condone/ agree with any sentiments expressed. Items are included purely for information purposes"

Please note: "Copyrights acknowledged. Please advise if unintentional infringement affects your rights"

August 17, 2012

Railway Gazette International News Feed... 17th August 2012

‎16 ‎August ‎2012, ‏‎15:09:00

London Underground pulls the plug on Powerlink PFI

‎16 ‎August ‎2012, ‏‎15:09:00Go to full article
UK: London Underground gave notice on August 16 that it intends to terminate the 30-year Powerlink private finance initiative contract for the operation and maintenance of its high-voltage electrical power network. LU will end the contract in August 2013 by exercising a half-way break clause. It will be required to make termination payments estimated at about £160m to the Powerlink shareholders in order to repay private financing facilities, but expects to make an overall saving of £225m over the next 15 years. LU Commercial Director Sarah Atkins said the PFI contract signed in 1998 was 'performing well', but early termination would provide increased operational flexibility and avoid future financing costs. The contract is with UK Power Networks Services Powerlink Ltd, which is owned by UK Power Networks (80%), ABB (10%) and Balfour Beatty (10%). Powerlink and LU will work together 'to ensure a smooth transfer of staff and activities back to LU'.

DB orders Traxx locomotives

‎16 ‎August ‎2012, ‏‎12:32:00Go to full article
GERMANY: Deutsche Bahn has placed a firm order for Bombardier Transportation to supply a further 32 Class 146 Traxx electric locomotives for regional passenger services. The €108m contract announced on August 16 an option on existing agreements. Delivery is planned for 2014, with the 160 km/h locomotives to be used with existing coaches and future double-deck stock. Bombardier has now sold more than 1 550 Traxx locomotives in 16 countries.

Gotthard alliance signed

‎16 ‎August ‎2012, ‏‎12:00:00Go to full article
EUROPE: Swiss Federal Railways and Italian infrastructure manager RFI have agreed to strengthen their co-operation on the Gotthard corridor ahead of the opening of the Gotthard Base Tunnel in 2016. Two agreements were signed by head of SBB Infrastruktur Philippe Gauderon and RFI Director Michele Mario Elia on August 3. With demand increasing for both passenger and freight traffic, more trains are using the transalpine route linking Zürich and Luzern to Milano, and the two operators foresee major challenges from 2014. SBB and RFI are to form joint working groups to address technical and operational issues, aiming to improve network utilisation and cut journey times. The Network Development team will oversee infrastructure projects such as extending platforms and providing clearance to carry 4 m high lorries. An Operations group will co-ordinate cross-border services to improve punctuality, and review timetabling to optimise capacity. The second agreement lays out 'tailored action plans' to equip lines on both sides of the border with ETCS to boost interoperability. The base tunnel is being equipped with ETCS Level 2, and SBB has already committed SFr300m to roll out Level 1 Limited Supervision on the existing route. A ceremony at Airolo on July 13 attended by representatives of the Swiss transport ministry, SBB Infrastruktur, Siemens and Thales marked the commissioning of the first Eurobalise being installed as part of the national rollout strategy, which is due to see the legacy ZUB and Signum equipment replaced by the end of 2017.

Yuxi - Mengzi line completed

‎16 ‎August ‎2012, ‏‎09:16:00Go to full article
CHINA: Construction of 141 km line from Yuxi, south of Kunming, to Mengzi on the route to the Vietnamese border was officially completed on August 14. Just over half of the route is on viaducts or in tunnel, reflecting the challenging local topography, and the 4·5bn yuan cost has been funded jointly by the Ministry of Railways and Yunnan province. Services are expected begin by the end of the year. Work is underway to continue the line from Mengzi to the Vietnamese border town of Lao Cai as a key element of China’s efforts to improve cross-border infrastructure. This section parallels the existing metre-gauge line which links the Vietnamese capital Hanoi with Yunnan province, but has speeds limited to just 30 km/h. The new route is primarily intended for freight, with a maximum speed of 120 km/h. It will form the easternmost of three north–south lines planned to link southwest China with neighbouring countries in the Asean community.

Wärtsilä engine on test in Russia

‎16 ‎August ‎2012, ‏‎05:00:00Go to full article
RUSSIA: The first TEM18V shunter produced by TMH’s Bryansk plant with a 882 kW Wärtsilä 20LA engine is undergoing field testing following certification by the federal railway agency. The Wärtsilä TMH Diesel Engine Co joint venture has announced plans for an engine factory at TMH’s Penzadieselmash plant, broadening the Finnish firm’s activities into the rail market and giving it a stronger industrial foothold in Russia. Up to 300 engines a year would be produced for locomotives, and other applications, in the CIS market.

Chemnitz orders electro-diesel tram-trains

‎15 ‎August ‎2012, ‏‎15:41:00Go to full article
GERMANY: Vossloh has won an order to supply eight electro-diesel tram-trains for the network under development around Chemnitz, with an option for two more. Delivery is planned for 2014. The €42·3m contract was signed by transport authority Verkehrsverbund Mittelsachsen on August 14, with funding from the Land of Sachsen and the European Regional Development Fund. The wheelchair-accessible CityLink tram-trains will 37 m long, with 94 seats and a top speed of 100 km/h. Vossloh Kiepe will be responsible for the traction and control equipment and air-conditioning, while Vossloh Rail Vehicles will provide body shells, bogies and interior fittings. The tram-trains will operate from the existing network's 600 V and 750 V DC overhead electrification, changing to diesel to reach Burgstädt, Mittweida and Hainichen along regional railway lines. These three routes form the first stage of a five-phase programme to develop a 226 km network of light rail services by 2020.

No comments:

Post a Comment

Tell us your Railway News!